Teesside's Research Repository > Theses > PhD Theses > Innovative methodology for location-based scheduling and visualisation of earthworks in road construction projects

Title: Innovative methodology for location-based scheduling and visualisation of earthworks in road construction projects
Authors: Shah, R. K. (Raj)
Advisors: Dawood, N. N. (Nashwan)
Dean, J. T. (John)
Castro, S. (Serafim)
Citation: Shah, R. K. (2011) Innovative methodology for location-based scheduling and visualisation of earthworks in road construction projects. Unpublished PhD thesis. Teesside University.
Publisher: Teesside University
Issue Date: 15-Nov-2011
URI: http://hdl.handle.net/10149/194590
Abstract: This thesis focuses on the development of an innovative location-based scheduling methodology and a computer-based model for improving earthwork operations in road construction projects. Analysis of existing planning and scheduling practices in road construction projects conducted in the course of this research concluded that planning, scheduling and resource allocation are largely dependent on subjective decisions. Also, shortcomings exist due to the distinct characteristics of earthworks, e.g. one-off projects with uncertain site conditions and soil characteristics, causing delays and cost overruns of projects. The literature review found that existing linear scheduling methods provide inaccurate location-based information about earthworks and fail to integrate different productivity rates. A survey was used to capture and analyse industrial practices and issues related to delays and cost overruns. This analysis revealed that the accurate location-based information is vital for efficient resource planning and progress monitoring. Following these findings, a theoretical framework and specification were developed to automate location-based scheduling and visualisation of information. A prototype model was developed by integrating road design data, sectional quantities, productivity rates, unit cost, site access points, and arithmetic algorithms. The algorithms underpinning the model enable the generation of time-location plans automatically as a key output of the model. Weekly progress profiles, space congestion plans, and cost S-curves are the other outputs. A cut-fill algorithm was developed to identify optimum quantities of earthwork and its associated costs. Experiments were conducted with design data provided by a road construction company to demonstrate the model‟s functionality. Sensitivity analysis was used to identify the critical factors relating to earthwork scheduling. It was found that the model is capable of generating time-location plans, considering the critical factors and location aspects. Finally, the model was evaluated using a case study and validated by road construction professionals using an indirect comparison method. It was concluded that the model is a valuable tool for producing location-based scheduling, optimising resource planning and assisting in the communication of scheduling information from the location viewpoints in the earthwork projects.
Type: Thesis or dissertation
Language: en
Keywords: time-space planning
communication of scheduling
cut-fill optimisation
weekly progress profiles
resource planning
Appears in Collections: PhD Theses
SSE Theses
Technology Futures Institute

Files in This Item:
File Description Size Format View/Open
194590.pdfFinal Thesis11532KbAdobe PDFThumbnail
View/Open
194590.pdfLicence Agreement (Administrator Use Only)620KbAdobe PDFThumbnail

Please use this identifier to cite or link to this item: http://hdl.handle.net/10149/194590
    Del.icio.us     LinkedIn     Citeulike     Connotea     Facebook     Stumble it!     Twitter    



All Items in TeesRep are protected by copyright, with all rights reserved, unless otherwise indicated.